8. EDITING MACHINING PROGRAMS
B–62444E–1/04
OPERATION
108
If a two–path lathe with the Series 16–TB is used, a process can be moved
between the two tool posts.
When the process is moved to the other tool post, the tools used in the
destination tool post is automatically selected. The tools required for the
process to be moved must be registered in advance.
Moving the process to the other tool post is the same as moving the
process for a tool post, except that the former requires the move
destination to be specified to the other tool post.
Moving the grooving process (process 03) of the HEAD–L to HEAD–R
on the process editing screen shown in Section 8.6.1
Move the cursor to process 03, then
[TRANS.]
Move the cursor to process 06, then
[EXEC]
After the operation above, the following process editing screen is
displayed.
EDIT THE PROCESSING PROGRAM *** PROCESS EDIT *** [CAP.: HEAD–L]
INITAL SET FC25 BAR
PROC (01) BAR OUTER END
ROUGH T0505
3M 0S
JJJJJJJJJJJJJJJ
PROC (02) BAR OUTER END
FIN T0505
1M37S
JJJJJJJ
PROC (04) TRANS.
0M20S
JJJ
RE–NUM TRANS
.
EDIT PLOT GUIDEDELETE COPY RETURN<
HEAD–L
HEAD–R
INITAL SET FC25 BAR
PROC (04) TRANS.
0M20S
JJJ
PROC (05) BAR OUTER END
ROUGH T0505
1M 3S
JJJJJJ
PROC (06) BAR OUTER END
FIN T0505
0M39S
JJJJ
PROC (03) GRV OUTER END (STNDRD)
T0909
0M 4S
J
HEAD–L 5M01S 01 JJJJJJJJJJJJJJJJ 02 JJJJJJJJJ 04 JJJJ
HEAD–R 2M02S 04 JJJJ 05 JJJJJJJ 06 JJJJJ 03
8.6.3
Moving a Process
between the Two Tool
Posts
Example