7.START-UP B-64004EN/02
- 110 -
7.1 START-UP OPERATION
The machine tool builder has to do tests for insulation and protective
bonding. Testing must be performed according to Chapter 19.2 and
19.3 of the standard IEC 60204-1 by an appropriately authorized
person and recorded.
Continuity of the protective bonding circuit
When the machine is installed and the electrical connections are
complete, including those to the power supply, the continuity of the
protective bonding circuit can be verified by a loop impedance test in
accordance with 612.6.3 of IEC 60364-6-61. For further details,
please refer to Chapter 19.2 of IEC 60204-1.
Insulation resistance tests
The insulation resistance measured at 500 V d.c. between the power
circuit conductors and the protective bonding circuit is to be not less
than 1 M Ω. For further details, please refer to Chapter 19.3 of IEC
60204-1.
7.1.1 Acceptance test and report for safety functions
Acceptance test for Safety function
The machine tool builder is to conduct a dual check safety function
check test during machine start-up operation.
In this test, limits need to be exceeded to check that the dual check
safety function operates normally.
Acceptance report
A qualified person is to check each dual check safety function and
record the test results in a check report.
NOTE
When modifying dual check safety function data,
conduct an additional check test on the modified
dual check safety function and record the test
results in a check report.
Safety-related I/O monitoring test
Data cross-check operation is tested with the I/O device connector
detached.
MCC off Test check
The test mode signal is used to check that a MCC off Test is
conducted.
Negative test:
Conduct a MCC off Test by disconnecting the MCC contact
signal (input). Check that an alarm is issued and the MCC
remains to be shut off.