Fig.5.20.6 shows a ladder diagram for the JMP instruction. When
ACT=0, the next step to the JMP instruction is executed. When ACT=1,
logical operations are skipped according to the specified number of coils.
Note that, when ACT=1, even if signal A changes from 1 to 0 or vice versa
as shown in Fig.5.20.6, W1 remains in a status before ACT=1. Similarly,
W2 remains unchanged, even if signals B, C, and D change. If a sequence
is executed in ladder split mode, even the use of the JMP instruction does
not reduce the execution time of the sequence (see Section I.2.3,
“Processing Priority”).
W1
JMP
(SUB 10)
ACT
2
W2
A
C
B
10.1
EF
W3
ACT=0
ACT=1
20.1
D
Fig. 5.20.6 Ladder diagram for the JMP instruction